According to the following procedure:
(1) Remove the top handrails and railings from the cross, then remove the scaffolding (or horizontal frame) and the escalator, and then remove the horizontal bar reinforcement bar and scissors.
(2) from the top of the cross-side began to disassemble the cross-support, simultaneously remove the top support wall and the top mast.
(3) continue to phase down the next step to remove the second step mast and accessories. Scaffolding free cantilever height shall not exceed three steps, or should be added temporary pull knot.
(4) continuous dismantling down. For even the wall pole, long horizontal bar, scissors support, must be dismantled in the scaffolding to the relevant gantry before being removed.
(5) Remove the sweeping pole, the bottom mast and the sealing rod.
(6) Remove the base, remove the pad and pad.

Pub Time : 2018-10-11 11:46:37 >> News list
Contact Details
Cangzhou Weisitai Scaffolding Co.,Ltd.

Contact Person: Sunny Feng | Eva Che | Edison Huang

Tel: +86-13731704301 | +86-17865358038 | +86-19531150731

Fax: +86-317-5569940

Send your inquiry directly to us (0 / 3000)